If I have a worksheet that had a beginning date column and
an ending date column. Is there a way to calculate (using
a formula) how many actual work days that is involved
minus week-end and holiday dates or do you have to know
some programming?

Thanks in advance, I really need this.
 
F

Frank Kabel

Hi Pam
have a look at the NETWORKDAYS function. It will do exactly what you
want (for more info see the Excel helpfile)

HTH
Frank
 
B

Bob Phillips

Pam,

The NETWORKDAYS does this

=NETWORKDAYS(A1,A2, B1:B10)

B1:B10 would be the list of holiday dates.

This is part of the Analysis Toolpak, so make sure it is installed.

--

HTH

Bob Phillips
... looking out across Poole Harbour to the Purbecks
(remove nothere from the email address if mailing direct)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top