I followed the FAQ "Create Stoplight Indicators" (Date Slippage) which
I was able to make work with no problem, but brings up a troubling
question. As I comprehend it, this compares the baseline finish to
the finish. (not the ACTUAL finish). If the finish column is created
only once, at the beginning of planning the project, from which the
baseline is created, and never updated, how can this help me? Only
the actual finish seems to be keeping track of what's--actually--
happening, thus, actual slippage.
thanks
Naomi