Dates don't equal the duration

N

Noel

MS Project 2003: When I change the duration of a task, the dates don't equal
the duration time. If the duration is 3 days, the dates are showing 4 days.
How do I fix this?
Thanks
 
J

Jan De Messemaeker

Hi,

First,, if you want to observe dates and duration exactly, you will have to
show tiime of day in your dates: Tools, Options, View, select the date
format thet is upmost in the dropdown list

Then read Faq 5. Default working hours in
http://www.mvps.org/project/faqs.htm

Hope this helps,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top