Default Baseline

H

hasan

Hi

How do I Default Baseline For Tracking Gannt
I want to Default Baseline (Baseline 2)
But Not Earned value for Tracking Gannt
 
J

JulieS

Hello hasan,

I assume you wish to show the Baseline2 bars in the Tracking Gantt
not the Baseline bars? If so, Format > Bar Styles change the
Baseline bar style to draw from Baseline2 Start to Baseline2 Finish.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
H

hasan

I Lowe Youuuuuuuuuuu
Thank you so much julies you wery make me happy :)
Thank you

"JulieS":
 
Top