Default number of Tasks in the My Tasks page

D

doc_tinker

Hi there.
I have tried to search the forums to see if this was already answered and
could not find the answer.
I am using PS 2007 server - RTM.
In the My Tasks page it shows 4 tasks listed there out of 9.
Is there a way to change this view to list all of the tasks assigned to a
resource?

thanks for any help.
 
M

Mark Everett | PMP

Hi there.
I have tried to search the forums to see if this was already answered and
could not find the answer.
I am using PS 2007 server - RTM.
In the My Tasks page it shows 4 tasks listed there out of 9.
Is there a way to change this view to list all of the tasks assigned to a
resource?

thanks for any help.

Doc -

If you have 9 published tasks that you are assigned to and only 4 are
showing, I suspect that you have the "Current tasks" switch checked
and that 5 of those 9 tasks are outside of the current task setting
(usually 10 days - two calendar weeks). On the My Tasks page, click
on Settings (on the toolbar) and then View Options and uncheck the
"Show current tasks only".

That should do it for you.

Mark Everett
www.catapultsystems.com
 
D

doc_tinker

Thanks Mark - that did it!

Mark Everett | PMP said:
Doc -

If you have 9 published tasks that you are assigned to and only 4 are
showing, I suspect that you have the "Current tasks" switch checked
and that 5 of those 9 tasks are outside of the current task setting
(usually 10 days - two calendar weeks). On the My Tasks page, click
on Settings (on the toolbar) and then View Options and uncheck the
"Show current tasks only".

That should do it for you.

Mark Everett
www.catapultsystems.com
 