Default units for Work on project server

S

Saj

I would like to configure the the project view to display
work in days.

I have changed Enterprise options and the Project options
the project view still displays work in hours.

Anyone know how I can fix this?

Saj
 
K

Kevin Flanagan

When I wen into my project, all I had to do was to
Choose Tools -> Options and click on the Schedule tab and
change work from hours to days and all my tasks converted
automatically.

Kevin
 
S

Sah

Yup,
On MS Project client this works as expected,
On Project Server Web Access changing the format thru the
client on Enterprise template and the published project,
seems to make no difference

Saj
 
K

Kevin Flanagan

I believe this is a local setting on a project by project
basis. Not all settings can be set in the Global.

Kevin
 