Default View in Project Pro

C

CARTON JEROME

Hello,

I would like define a default view for new project and for existing project.

Anyone can help me ?

Thanks.
 
G

Gérard Ducouret

CARTON JEROME,

In Project Professional:
Tools / Options / Views : Default view: what you want in the list

Gérard Ducouret
 
C

CARTON JEROME

Thanks. It works for new projects.

It doesn't work when opening existing project. When opening existing
project, the project is open on the last view selected in the project, not
the default view.
 
R

Robert

Jerome,

Yes, it is the default behavior of Project.
To do what you want on existing projects, you will have to write an autorun
VBA procedure.

Gérard Ducouret
 
Top