Marcos --
Do the following to delete a base calendar:
1. Log into Project Server through Microsoft Project Professional with
administrator permissions
2. Open the Enterprise Global
3. Click Tools - Organizer
4. Click the Calendars tab
5. On the right side of the dialog, select the base calendar to be deleted
6. Click the Delete button then click the Close button
7. Save and close the Enterprise Global