detail application on material quantities on resource sheet

V

vergel

im having problem on how to make an input of detail application of material
quantities on resource sheet. ms projects just sets the cost and percetage of
the material but what i want to see is the detail quantities of any material
that i put in the resource sheet. would anyone please tell me on how to solve
this problem.. thanks
 
R

Rod Gill

Project doesn't make a good Job Cost tracker. However once you have basic
Material entered in the Resource sheet (EG Concrete m3) then assign units of
material on individual tasks.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
Top