Stephen:
I don't know about saving versions of Master Plans; if the system allows it,
or what you might get out of it. I don't think it makes sense in the Project
Server environment. Master projects do not contain the details of the
subprojects, so there's little value that isn't easily exceeded by using a
baseline.
--
Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com
-
Stephen Eyton-Jones said:
Hi Gary...I'd like to expand on this....
So, if I take that one step further, and create a version called .master
and create a master project with all the linked projects now 'internalized'
(all data in the project) into the master and save it into the Server and
publish it as a .master, can I then have access to a master project that I
can view and work with in views and assure myself that they will not double
count my resources or be considered for resourcing? I would redo this
linking and saving process monthly (probably save a shell of the linked
project(s)) and saving as an all in one project as a snapshot of the current
master plan that we would report from for that month. The key is in being
sure I don't mess up the resource assignments etc.
I realize that I could likley do the same in an MPP file but that data
would not be available to PWA users, which is my goal.