Itzik --
When the OLAP cube rebuilds, it only uses the latest published project
information from each project. After each project manager updates a
project, he/she should also click Collaborate - Publish - All Information or
Collaborate - Publish - Project Plan to "push" the latest project
information to PWA for updating in the OLAP cube on its next rebuild. If
you have one or more projects in your company's portfolio that have been
updated but NOT republished, then there will be differences in values
between the Portofolio Analyzer and the Resource Usage view in Project
Professional. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"