Arjun M said:
Mike,
I did that.
Now i have the following issues.
I have a manual tab on my machine.
But my colleague has automatic tab turned on. When we pressed F9 the
dates changed only in my machine. So now I am in a fix. The dates on my
project plan have come after extensive work with the architects.
So I want the dates on my machine to remain. But all the other machines
have automatic tab on. So when they open my plan I want them to see the
dates in my plan.
Please advice to tackle this problem.
Thanks
Arjun M
Arjun,
If you had a schedule that was not calculated, (i.e. calculation was set
for manual), then you did NOT have a valid schedule. Just because you
happen to like the dates you had does not mean they are any good. Task
dates in a schedule should be the result of estimated durations, task
links, task work and resources assigned.
How did you arrive at the dates with the architects? It sounds like they
are rather arbitrary or perhaps the DESIRED dates but not based on any
schedule logic. This is the same issue that I explained in your other
post. Fixed dates do NOT make a schedule. Fixed dates do NOT make a
schedule. Fixed dates..........
If a dynamic schedule, (i.e. a schedule that Project calculates based on
the data given to it), is not giving the desired output, then you need
to review the schedule and see where schedule logic can be changed, more
resources can be utilized, estimated durations can be refined, and any
number of other schedule adjustments that will give a better more
acceptable plan. But do NOT simply tweak the schedule to hit some
arbitrary dates that a group of people decided they liked. Reality isn't
always popular and you might just find that you can't get there from
here. Come up with a new plan but if the plan is artificial and not
based on historical actuals or other valid criteria then the plan is
most likely going to fail and everyone is going to be upset.
John
Project MVP