All dates on a gantt chart in the left hand column are showing as 01/06/2006
but the dates on the top row are showing as 01/06/2007. I have never used MS
Project. I am trying to help someone.
Any help is appreciated.
Thanks
 
R

Rod Gill

Looks like you have entered a financial year that is different from the
calendar year. Select Tools, Options, Calendar tab and set financial year
start to January

or

Double-click anywhere on the timescale and if your version of Project
supports it, deselect the Use Fiscal year option.
 
R

Ravi

Thank you Rod.
That did the trick,

Ravi

Rod Gill said:
Looks like you have entered a financial year that is different from the
calendar year. Select Tools, Options, Calendar tab and set financial year
start to January

or

Double-click anywhere on the timescale and if your version of Project
supports it, deselect the Use Fiscal year option.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top