Chiraz
Hi,
I have inserted 10 projects into a master project file and baselined the
project. When i update the schedule the actual start date and finish date is
accepting the baseline start and finish dates. In reality actual start and
finish dates are bit different?
Eg:
Baseline Start: 01/01/2009 Actual Start Date: 05/01/2009
Baseline Finish: 03/01/2009 Actaul Finish Date: 08/01/2009
But upon updating the % complete the actual start and finish dates is
recording as Baseline start and baseline finish dates. But i want it to
record Actual start and actual finish dates instead.
Thank You,
I have inserted 10 projects into a master project file and baselined the
project. When i update the schedule the actual start date and finish date is
accepting the baseline start and finish dates. In reality actual start and
finish dates are bit different?
Eg:
Baseline Start: 01/01/2009 Actual Start Date: 05/01/2009
Baseline Finish: 03/01/2009 Actaul Finish Date: 08/01/2009
But upon updating the % complete the actual start and finish dates is
recording as Baseline start and baseline finish dates. But i want it to
record Actual start and actual finish dates instead.
Thank You,