Different Duration calculation in Project and Web Access

Y

YMA

Hi

My staff is scheduled 7 hours a day in Ms-Project. All
the parameters are set to work with this calendar. The
duration is set to 7 hours a day. For exemple, for a one
year project the duration is 248 days of work including
13 holidays.

When I switch to Web ACCESS, for the same project, the
duration changes to 217 days. I think the duration is
set to 8 hours a day. Can I change this parameter in Web
ACCESS and where can I do so?

Thanks
 
M

MutazAG

check KB 331973 http://support.microsoft.com/?id=331973 (PRJ2002: Work
Duration Is Calculated By Eight Hours per Day, Even if Working Hours Are
Changed)

there you'll find a workaround and a hotfix.


to obtain the hotfix you have to report the problem to microsoft. it is
recommended to have you
 