Hi,
I want to assign different Rates for a single enterprise resource, with same
effective date, on different projects. Here is what I want to do:
Suppose a resource A is working on two support project. The Projects are for
whole year starting Jan 1st and ending Dec 31st. In Project 1 the rate is
50 and in project B the rate is 75. How can I do that?
If it is not possible, please some one confirm
Any response will be highly appreciated.
Regards,