Different values of finished percent

N

Nara

Hi!

I´m updating the % finished of a Task on the ProjectProfessional, but the
same information in Task Grid on ProjectWebAccess does not show the same
value.
What can I do to see the same value on both applications?
The project has been saved on server. All the informations are published,
but I still see different values of % finished.
Please, help...

Thanks!

Nara
 
D

Dale Howard [MVP]

Nara --

When you manually enter actuals in the Microsoft Project plan, you MUST do
the following to "synch up" the actuals between the project and the PWA
timesheet page of the team member(s) assigned to the task:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resource" option
3. Click OK

Hope this helps.
 
Top