S
S Belling
Project Web Access and Project Professional having a
difference of opinion regarding completed tasks:
We'll open a project in Project - use Task Information to
update a project task to 100% complete. Save and republish
the project.
We'll go into PWA - we'll look at Task view - see that the
task we just updated to 100% complete does not have the
little checkmark of "doneness" but in fact has the
little ! indicating a message that the task is late.
Then, we'll look at this same project in Project view
(PWA) and see various views acknowledging that the task is
indeed 100% complete.
Any ideas on why this is?
Thanks,
S Belling
difference of opinion regarding completed tasks:
We'll open a project in Project - use Task Information to
update a project task to 100% complete. Save and republish
the project.
We'll go into PWA - we'll look at Task view - see that the
task we just updated to 100% complete does not have the
little checkmark of "doneness" but in fact has the
little ! indicating a message that the task is late.
Then, we'll look at this same project in Project view
(PWA) and see various views acknowledging that the task is
indeed 100% complete.
Any ideas on why this is?
Thanks,
S Belling