Environment Details:
We are currently using MS Project 2003 Enterprise. We have also turned on
the protected actuals feature.
Issue:
We have tasks that are assigned to resources who then book time in PWA.
This works fine until you want to "prevent" them from booking any further
time to your plan. Is there a way, without deleting the actual resource
assignment, of disabling a resource from booking to your task? We do not
want to lose the history of what has already been booked to the task, just
prevent future bookings.
Thanks in advance for your help!
We are currently using MS Project 2003 Enterprise. We have also turned on
the protected actuals feature.
Issue:
We have tasks that are assigned to resources who then book time in PWA.
This works fine until you want to "prevent" them from booking any further
time to your plan. Is there a way, without deleting the actual resource
assignment, of disabling a resource from booking to your task? We do not
want to lose the history of what has already been booked to the task, just
prevent future bookings.
Thanks in advance for your help!