Disable tracking

L

Luis Arguello

Hello!

I'd like to know if there's a way to disable a project from being tracked by
team members. I would like to show the project in the Project Center as
"closed" and not to allow team members to track any more hours or effort for
it.

Thanks in advance for your help!

Luis D.
 
P

Paul Conroy

You can use "Close Tasks to Update" to prevent any further updates.

This is set from PWA, Server Settings, Time & Task Management, Close Tasks
to Update.

Alternatively you could use category permissions to prevent users from
updating this data.

I would in each case recommend setting remaining work to zero for all
uncomplete tasks, so as to remove the "Noise" from users "My Tasks"

HTH

Paul
--