nice answer Dale, may be an answer for your projectexperts Q&A portal

greetings from Australia
--
Marc Soester
State Manager: EPM
:
Doug --
You will need to use several tricks to make this happen since the
Status
Date field is not an available field in Project Center views. Here's
the
tricks:
1. Open the Enterprise Global field and name a custom enterprise
Project
date field as something like My Status Date. Add the [Status Date]
formula
to the field and save the custom field changes. Save and close the
Enterprise Global file, then exit and relaunch Microsoft Project
Professional.
2. Ask your PM's to open each project, to click Project - Project
Information, and to make sure they have entered a Status Date for their
project. After doing so, they should click the OK button and then
press the
F9 function key to recalculate the project. They should click
Project -
Project information again to confirm that the My Status Date field has
picked up the correct Status Date information and then click OK. After
doing this, they should click Collaborate - Publish - All Information
to
"push" the My Status Date field for the project to PWA.
3. You should add the My Status Date field to your Project Center
dashboard
view in PWA.
Hope this helps.
How can I display the last status report date for a project? I want
to
add
that date to my "Dashboard" view I created for all projects. Since
we
have
an issue with PM's not submitting timely status reports, our PMO
wants to
see
the status date in the dashboard view.