Dear all,

Although I have set the "Work is entered in" as Days in
"Options->Schedule", the unit in "Work" in the Resource Usage View in
Resource level is displayed as hours. However, in task level, they are
displayed as Days. Does anyone know why? Thanks in advance.

Rgds,
Ryan
 
D

Dale Howard [MVP]

Ryan --

You must specify this Options value in each individual project. You cannot
set it in the Enterprise Global file. I tried making the setting in an
individual project, and Work was displayed in Days in the Resource Usage
view. Hope this helps.
 
D

David Brock

How can I get Work to display in days in Project Center and Resource Center,
rather than hours as it does now?
 