Display work in days not in Hrs

X

xavier

Hello,
How is it possible to set in PWA the Work display in days not in hrs.
In Project, this can be set in tools, option.

Thank's in advance,
Xavier
 
S

Stefano Scheda

I have the same problem. On PWA (Project Task Summary view and other views)
Duration is expressed in days and Work in hours, while opening the
enterprise project in MSPrj the Work is expressed in Days.
Both the project options and the Enterprise Global options are set as "Work
in entered in days", but PWA still shows Work in hours.

tia,
Stefano
 