I am new to Project Server and need basic step by step on adding columns to a
project plan that can be viewed in PWA. I have created a project plan in MS
Project Professional 2007 using the default Gantt view and not as an
Enterprise Global template.
Added a column called Month and input data, 1, 2, 3. Added column to
Enterprise.
In PWA I can add the column to a view in My Assignments and see the column
but the data in the Microsoft Project Plan does not show up in the My
Assignments column.
I have read alot of the posts and am not sure which step I am missing.
project plan that can be viewed in PWA. I have created a project plan in MS
Project Professional 2007 using the default Gantt view and not as an
Enterprise Global template.
Added a column called Month and input data, 1, 2, 3. Added column to
Enterprise.
In PWA I can add the column to a view in My Assignments and see the column
but the data in the Microsoft Project Plan does not show up in the My
Assignments column.
I have read alot of the posts and am not sure which step I am missing.