I am attempting to build a project dashboard using a project center view with
a number of enterprise fields. I would also like to display the milestones
at the stage level of the project plan (e.g Assessment Complete, Development
Complete, Testing Complete, etc.). The only way I have determined to display
this type of info is by using enterprise date fiels; however, this has to be
updated manually. Is there a way to have this data display and be dynamic so
that if the milestone date changes it is reflected in my "Dashboard" view at
the project level?

Thanks!
 
J

JJHayesIII

Simmons_RJ said:
*I am attempting to build a project dashboard using a project center
view with
a number of enterprise fields. I would also like to display the
milestones
at the stage level of the project plan (e.g Assessment Complete,
Development
Complete, Testing Complete, etc.). The only way I have determined to
display
this type of info is by using enterprise date fiels; however, this
has to be
updated manually. Is there a way to have this data display and be
dynamic so
that if the milestone date changes it is reflected in my "Dashboard"
view at
the project level?

Thanks! *

the way we've dealt with this is to have a standard template with set
milestones, and wrote custom reports to only pull the data for those
specific summary tasks

another method that might be helpful is to use the "Roll up milestone
to top" option, but i don't know if this setting holds for in web views
 