displaying other projects name with the administrative tasks

B

Basim

Hi,


I have implemented administrative project .

when i open administrative project in project professional and see the
report administrative tasks which i assign to the resources then in the
project professional report the resource which is working on other projects
..

other projects name are also displaying with the administrative tasks name
and their actual hours also I dont know why .

when i open the administrative project and i only want to see the actual
hours of their tasks only .

pls solve this problem

regards

basim
 
D

Dale Howard [MVP]

Basim --

If you open an enterprise project in Microsoft Project Professional and
apply the Resource Usage view, you will see each resource's tasks in the
active project, PLUS a single line representing the resource's tasks in
other enterprise projects as well. This is the default behavior of Project
Server. To overcome this limitation, refer to the following link:

http://www.projectserverexperts.com/Shared Documents/ViewResourceInformationForActiveProject.htm

Hope this helps.
 
Top