Dissapearing Tasks - Project Server 2003

D

David.A.Steyn

I have a project plan with around 1600 tasks, when publishing,
notifications go out successfully and resources can see their tasks in
PWA.

When viewing the project from the project center, tasks above ID
number 1200 or therabouts do not display. As noted above, resources
assigned to tasks with ID numbers above that point can see and report
on tasks in the number range not showing from tasks view.

Any ideas, have done all the obvious like republishing, checking
viewdrop folder, service packs, recreating the views etc.
 
S

Scott M Wagner - MVP

David,

I have seen this before.
Please make an offline copy of the project, save the file offline as XML.
Do not delete the offline file.

Delete the online file only.
Re-import the xml version of the project.
When I have seen thios befor it was because someone copied tasks from one
section of the project file to another. The server retained the GUID for the
task ID's and they then would not publish properly.

Hope that works, let me know.

Thanks,
 
Top