disturbed values due to unmanaged period

M

Micheal

Hi,

I have changed configure settings from managed periods to unmanaged periods
for five minutes and then republish assignments with " overwrite actual work
option"

and when I come into managed periods option and check the report in the
administrative project through project professional all entered hours of
users are disturbed and there values are changed into different values with
decimal.
I dont know why it is happen .
pls tell me how i can resolve this problem and restore the values into
previous position.
although I synchronize the project with the orignal values but the values
are not restored


pls help me to resolve this problem.

Regards

Micheal
 
M

Minhchau

I'm experiencing the same problem with switching back and forth between
unmanaged and managed period. My future tasks were splitted and extended
beyond the original finish date. Have you come up with any solution to fix
those corrupted projects yet?
Thanks,
 