R
Ryan
Hi all. I could use some advice on how to approach some document sharing
issues I've come across using Project Professional 2003 and Project Server.
First of all let me explain how our users use the software. We have 1
primary project manager who uses Project Professional 2003 exclusively. He
would prefer to stick with that and not have to use PWA for any reason.
There are then about 10 users (resources) who use PWA and do not have
licenses for Professional 2003. Here's my list of issues:
1) Attachments or links that the project manager adds to tasks using
Professional 2003 do not appear in PWA.
2) Documents uploaded to the PWA document library and then attached to tasks
do not show up in Professional 2003.
So you see my problem here. The project manager cannot see documents that
users add, and users cannot see documents that the project manager adds.
Also not all files can be stored on the project server because they are
created by and used by other departments who do not use Project and have no
desire to do so. Ideally I would like to be able to attach links to tasks
that are viewable through both PWA and Project Professional. Is there any
way to do this? Also I would like documents that are uploaded to PWA and
linked to tasks to also be viewable through Professional.
Thanks for any help,
Ryan
issues I've come across using Project Professional 2003 and Project Server.
First of all let me explain how our users use the software. We have 1
primary project manager who uses Project Professional 2003 exclusively. He
would prefer to stick with that and not have to use PWA for any reason.
There are then about 10 users (resources) who use PWA and do not have
licenses for Professional 2003. Here's my list of issues:
1) Attachments or links that the project manager adds to tasks using
Professional 2003 do not appear in PWA.
2) Documents uploaded to the PWA document library and then attached to tasks
do not show up in Professional 2003.
So you see my problem here. The project manager cannot see documents that
users add, and users cannot see documents that the project manager adds.
Also not all files can be stored on the project server because they are
created by and used by other departments who do not use Project and have no
desire to do so. Ideally I would like to be able to attach links to tasks
that are viewable through both PWA and Project Professional. Is there any
way to do this? Also I would like documents that are uploaded to PWA and
linked to tasks to also be viewable through Professional.
Thanks for any help,
Ryan