E
Evan
A client of mine had this question, and I had a halfway finished response,
but realized I needed cleverer minds that I to help me.
I have a master schedule that shows resources actuals overallocated in the
past. Since I let Project allocate the actual hours ( I enter them on a
weekly timescale) I will probably get numbers that have 10 hours one day, 2
hours the next and so on. As long as the weekly resource is not working over
40 hours a week, the EVM should not be affected I am guessing. Please let me
know if I am mistaken.
For future overallocations, I don't think the BCWP or BCWS is affected, but
the ETC might be. To me, that affect would be insignificant since the EAC
would stay the same if the total remaining work was correct, despite
overallocations at different intervals changing the slope of the ETC line
(graphed out in Excel).
I hope I am making sense, if I am please let me know if I am crazy in my
thought process.
but realized I needed cleverer minds that I to help me.
I have a master schedule that shows resources actuals overallocated in the
past. Since I let Project allocate the actual hours ( I enter them on a
weekly timescale) I will probably get numbers that have 10 hours one day, 2
hours the next and so on. As long as the weekly resource is not working over
40 hours a week, the EVM should not be affected I am guessing. Please let me
know if I am mistaken.
For future overallocations, I don't think the BCWP or BCWS is affected, but
the ETC might be. To me, that affect would be insignificant since the EAC
would stay the same if the total remaining work was correct, despite
overallocations at different intervals changing the slope of the ETC line
(graphed out in Excel).
I hope I am making sense, if I am please let me know if I am crazy in my
thought process.