C
caryle
Hi,
I know that this defeats the purpose of Project & Project Server but
we do not want to have the time entered in a task to change the actual
project. If the task is supposed to take 2 days but the resource
works on it for 3 days then the end date of the task changes. We
don't want this to happen but we do want to keep track of the number
of hours of work on each task.
Is there a way to configure Project Server 2003 to not update the
project?
Thanks,
Caryle
I know that this defeats the purpose of Project & Project Server but
we do not want to have the time entered in a task to change the actual
project. If the task is supposed to take 2 days but the resource
works on it for 3 days then the end date of the task changes. We
don't want this to happen but we do want to keep track of the number
of hours of work on each task.
Is there a way to configure Project Server 2003 to not update the
project?
Thanks,
Caryle