Double reporting to the PWA

Y

Yoav

I want to assign 2 resources to a task and to enable the resources to update
2 fields (a field per user) via the PWA.
Can the Project Server process 2 reports for the same task?
Environment: MSP2003 Server.
Thanks!
 
Y

Yoav

Hi, Gary. Thanks for your time!
Using "Published Fields" I added 2 Enterprise fields. Lets call them
EnterpriseText1 and EnterpriseText2.
I assigned 2 resources to a task, and I expect resource A to update, using
Tasks tab, EnterpriseText1 ; and resource B to update EnterpriseText2.
(I assume that Project Server does not allow to set permissions for the same
record. i.e. for a specific task, resource A and will not be able to update
EnterpriseText2 and resource B and will not be able to update
EnterpriseText1. am I right??).
Now, after each resource updates his field for the specific task
(EnterpriseText1 by resource A; EnterpriseText2 by resource B) I'm accepting
those requests by "Updates" tab. I see both updates in the PWA, but when the
data is uploaded to the Professional, only the latter request is updated to
the Pro. The former just is not presented.
I hope my dilemma is clear now.
 
Y

Yoav

Gary,
It makes some sense. What fields can be split by assignments - work, rem
work etc?
Is there a workaround for updating Enterprise Fields by different users? For
example, updating assignemt.text1 field and copying it to task.text1 field (I
don't know whether that's even makes sense)?
Thanks for your time,
Yoav
 