Double Tasks in PWA

M

Marty

Has anyone encountered double tasks displaying in Project Web Access, but
they show as single tasks in Project Server?
 
G

Gary L. Chefetz [MVP]

If you are using 2003, and you really should specify that, it may be that
you published tasks from both an individual project and a master project
containing that project. Does this help? If not, please let us know which
version you are using.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 
Top