Drag a gantt bar into the future and automatically update meetings

S

Serge

I would like to allow a user to drag a gantt bar into the future and
automatically update meetings' contraints, to within their newly updated
phase time frame.

Serge
 
R

Rod Gill

This is a development group, so what do you want to program? With VBA? PSI?

If manually, Project lets you do this already.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Serge said:
I would like to allow a user to drag a gantt bar into the future and
automatically update meetings' contraints, to within their newly updated
phase time frame.

Serge

__________ Information from ESET Smart Security, version of virus
signature database 5151 (20100527) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5151 (20100527) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
J

Jan De Messemaeker

Hi,

You will need VBA programming for that as indeed, constraints don't move
automatically with other tasks. Even then it is not obvious to record the
time you dragged a bar - you will have to record one of the baselines almost
continuously to record the times before the drag, somehow indicating to
which task the meetings should react..

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top