Draw task bars in relation to slack on detailed gantt

A

Anita

On my detailed gantt chart view I am displaying the task bars (blue) and the
amount of slack (green) at the end of each task with the amount of slack
displayed as text at the end of the bar. I also have a progress line drawn
on the view. What I would like to do is draw the task bar so that it starts
at the end of the slack rather than at the beginning so that my progress line
doesn't show my tasks being behind. Is this possible using Project 2007? Any
help gratefully received, hope that makes sense.
Thanks, Anita
 
A

Anita

That worked thanks! The only thing is now that some of my slack lines that I
had drawn in have disappeared and I'm not sure why - any ideas?
 
M

Mike Glen

Hi Anita,

The lines on the Gantt Chart are drawn in the order that they appear in the Bar Styles dialog. Check that they are in the correct order to prevent overwriting of what you want to see.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


That worked thanks! The only thing is now that some of my slack lines that I
had drawn in have disappeared and I'm not sure why - any ideas?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top