nickc
Exception days are messing with my with recurring tasks, causing repeats. I
have the 12/24-12/25 holidays in as exceptions, and the recurring task I have
out through 12/09 shows Monday, 12/28 5 times? There are other dates which
also repeat. Obviously, this is showing as over allocated on resources. Is
there something I'm doing causing the dates to repeat?