J
jetfan
I am creating a project where I set up about 25 tasks, input durations, and
resource loaded. These 25 tasks are to be repeated about 30 times because we
are designing the same equipment in sequence. I went ahead and copied the
initial tasks under the original 25, changed one predecessor and project
pushed out the new task start dates which appears fine on the Gantt chart.
However, when I go into the Resource Usage report, it duplicated the Resource
Names. I would like it to only show the Resource Names one time and carry
the work hours out across the page. Should I copy the tasks in a different
way? What I am doing wrong?
Thanks for the help.
resource loaded. These 25 tasks are to be repeated about 30 times because we
are designing the same equipment in sequence. I went ahead and copied the
initial tasks under the original 25, changed one predecessor and project
pushed out the new task start dates which appears fine on the Gantt chart.
However, when I go into the Resource Usage report, it duplicated the Resource
Names. I would like it to only show the Resource Names one time and carry
the work hours out across the page. Should I copy the tasks in a different
way? What I am doing wrong?
Thanks for the help.