Duplicate task generated in unrelated Project Plan

D

David Parker

I have a PM who has ownership of two separate plans. Somehow a task
from one plan duplicated itself to the other plan in the
msp_web_assignments table. This duplication is only seen through web
access, it is not in the project tables. It showed up with a very
high task_uid of 16777253, way beyond our largest task_uid. When I
check the other database tables, there is no sign of this new
task/assignment anywhere.

By the way, this is not the duplicate plan issue. Only the task is
duplicated, and on a totally different plan.

Any help will be greatly appreciated.

David Parker
 
Top