Dale,
I think I just figured out what I did (and it's not good....)
I believe I made a mistake last week when I updated the project status. I
used the "Update Project Progress" feature (Collaborate -> Update Project
Progress) instead of "Update Project" feature (Tools -> Tracking -> Update
Project)
I'm guessing that the Update Project Progress feature must have overwritten
existing data in PWA. Since I'm doing manual udpates (for a variety of
reasons) the PWA and Project DBs are not in synch and I don't want they be.
Can you confirm for me what the Update Project Progress feature does. Does
it take the actuals from Project Pro and download them to PWA?
I can see where this would explain the missing time data (if it wasn't in
Project Pro, then it would have been overwritten...) but would it also
explain the duplicate tasks?
If so, will restoring just the PWA database to its state as of two weeks ago
and then publishing the existing plans back to PWA get me back to where I
need to be (minus last week's PWA entries?)
Any thoughts and/or words of wisdom will be greatly appreciated.
--
Michelle Colodzin, PMP
Dale Howard said:
Michelle --
The behavior you see is usually caused by creating a master project and then
publishing the assignments in the master project, which causes duplicate
assignments on each user's timesheet in PWA. Would that explain your issue?
Let us know.