R
Ryan Reed
I can't find much documentation on this issue so I'm hoping someone here
will have a quick answer.
My Project Plan manager reports that in Project Web Access, when she clicks
Resources then selects "View resource assignments" and "All assignments" for
a specific resource, some of the resource's tasks are appearing twice in the
resulting list. One of the items has "(assignment)" appended to the end.
Each item also appears to have different actual hours worked attributed to
them.
As far as I can tell, the only action taken on these tasks recently is that
we republished them in Project Professional (Collaborate -> Republish
Assignments...) to put them under a new manager for approvals, etc
Can someone help me with (1) what the duplication means, (2) what caused it,
(3) how to reconcile it/make it go away?
Thanks in advance for your help.
Ryan
will have a quick answer.
My Project Plan manager reports that in Project Web Access, when she clicks
Resources then selects "View resource assignments" and "All assignments" for
a specific resource, some of the resource's tasks are appearing twice in the
resulting list. One of the items has "(assignment)" appended to the end.
Each item also appears to have different actual hours worked attributed to
them.
As far as I can tell, the only action taken on these tasks recently is that
we republished them in Project Professional (Collaborate -> Republish
Assignments...) to put them under a new manager for approvals, etc
Can someone help me with (1) what the duplication means, (2) what caused it,
(3) how to reconcile it/make it go away?
Thanks in advance for your help.
Ryan