Duration Based tasks planning

K

Karti

Hi,
How can we do the scheduling for a duration based tasks. Like a particular
chemical synthesis takes 12 hours irrespective of the no. of people assigned
to that task.
Thanks for the help in advance.
 
M

Mike Glen

Hi Karti,

Welcome to this Microsoft Project newsgroup :)

I would use elapsed times - enter 12eh for elapsed hours - which was designed for just this purpose.

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Hi,
How can we do the scheduling for a duration based tasks. Like a particular
chemical synthesis takes 12 hours irrespective of the no. of people assigned
to that task.
Thanks for the help in advance.
 
K

Karti

Thanks for your time.
Both of the methods work.
@Mike: Thanks for the link too.
Hi Karti,

Welcome to this Microsoft Project newsgroup :)

I would use elapsed times - enter 12eh for elapsed hours - which was designed for just this purpose.

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Hi,
How can we do the scheduling for a duration based tasks. Like a particular
chemical synthesis takes 12 hours irrespective of the no. of people assigned
to that task.
Thanks for the help in advance.
 
M

Mike Glen

You're welcome, Karti

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Thanks for your time.
Both of the methods work.
@Mike: Thanks for the link too.
Hi Karti,

Welcome to this Microsoft Project newsgroup :)

I would use elapsed times - enter 12eh for elapsed hours - which was designed for just this purpose.

FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials



Hi,
How can we do the scheduling for a duration based tasks. Like a particular
chemical synthesis takes 12 hours irrespective of the no. of people assigned
to that task.
Thanks for the help in advance.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top