D
DavidC
I have a project covering a number of companies using slightly different
hours of work. The programme I am developing is a high level programme which
reflects major groups of activities from each of the participating companies.
I have set up a specific calendar for each company as well as the standard
project calendar. I have also set the default settings to reflect the
standard project hours of 10 hours per day, and 7 days per week. I have just
noticed an issue when applying durations in days to a task and applying the
relevant companies calendar to that task.
To explain the phenomena this is an example:
Company 1 task has a duration of 10 days on the standard daily work time of
10 hours. If the task starts on the tenth, the task shows as being completed
on the 19th. Reflecting the 10 day duration.
Company 2 task also has a duration of 10 days, but they only work 8 hours
per day. The task starts at the same time (the 10th) but it shows a
completion date of the 22nd or 12.5 days, yet the duration still only shows
as ten days.
I have tracked this phenomena down to the way duration is stored in project
(duration days*default hours*60*10), and hence if a calendar works less hours
then the task is spread out to fulfill the total hours calculated using the
default hours of work not the hours of work of the relevant calendar. If I
set the companies calendar to the default, then the tasks show as completing
at a time outside the hours of work for that company and they complain. If I
set the calendar, then the calendar days covered by the duration are greater
than reality.
Is there a suitable work around or do I simply have to explain to the
contractor to ignore the time aspect of the finish date?
hours of work. The programme I am developing is a high level programme which
reflects major groups of activities from each of the participating companies.
I have set up a specific calendar for each company as well as the standard
project calendar. I have also set the default settings to reflect the
standard project hours of 10 hours per day, and 7 days per week. I have just
noticed an issue when applying durations in days to a task and applying the
relevant companies calendar to that task.
To explain the phenomena this is an example:
Company 1 task has a duration of 10 days on the standard daily work time of
10 hours. If the task starts on the tenth, the task shows as being completed
on the 19th. Reflecting the 10 day duration.
Company 2 task also has a duration of 10 days, but they only work 8 hours
per day. The task starts at the same time (the 10th) but it shows a
completion date of the 22nd or 12.5 days, yet the duration still only shows
as ten days.
I have tracked this phenomena down to the way duration is stored in project
(duration days*default hours*60*10), and hence if a calendar works less hours
then the task is spread out to fulfill the total hours calculated using the
default hours of work not the hours of work of the relevant calendar. If I
set the companies calendar to the default, then the tasks show as completing
at a time outside the hours of work for that company and they complain. If I
set the calendar, then the calendar days covered by the duration are greater
than reality.
Is there a suitable work around or do I simply have to explain to the
contractor to ignore the time aspect of the finish date?