Duration field not calculating

  • Thread starter Steve Douglas P2p, MCP
  • Start date
S

Steve Douglas P2p, MCP

Hi all, I have a very annoying issue, which i hoep someone can help
with. None of our projects are calculation the duration field.

I have tried a task types etc, and the duration is always 1,
regardless of the work entered.

I have selected calculate automatically from the options tab, but
still to no avail.

grateful for any help on this, as loosing hair by the minute.

Many Thanks
 
G

gaba53

What fields are you changing and what happens, what do you want to
happen? What is your task type currently set to and is effort driven
selected?
Do you have resources assigned?

I have not been using this program as long as most people here, but I
do know that it calculates duration by the following formula Duration
= Work X Units. If the resource field is blank Project sees 0 units
and doesn't like to calculate duration. Also try pressing F9 to
calculate now, just for fun.
 
Top