S
sslate
I'm using Project 2007. I have a summary task with several subtasks, all of
which have a 3 week combined duration to complete. The subtasks are not
predecessors of one another, they are all independent tasks using the same
resource. I want to show them independently, but not have the resource show
a daily overallocation. How can this be done?
which have a 3 week combined duration to complete. The subtasks are not
predecessors of one another, they are all independent tasks using the same
resource. I want to show them independently, but not have the resource show
a daily overallocation. How can this be done?