Duration in Hours in Project Web Access?

J

John Rutledge

Is it possible to display the Duration in hours in Project Web Access? I
would think this would be customizable, but if it is, I can't find it.

Thanks ahead,
-- John Rutledge
 
D

Dale Howard

John --

To the best of my knowledge, Duration is always shown in days in PWA. Hope
this helps.
 
M

MutazAG

Duration in PWA is always in hrs.

a workaround is to create an Enterprise Task Text field, set it to formula,
and use the function ProjDurConv to convert the [Duration] field to whatever
format u like.

then go to PWA, and modify the required view by adding the new customized
field to the fields list.

ofcourse this requires recalculating and republishing for project plans that
are already there in the database.

hth,
- mutaz
 