We recently deployed EPM in my department. I have been training everyone that
will be managing projects. A very weird thing we have noticed is that once a
project is published and you check it in PWA, a task that had, say, a 50 day
duration in Project now has a 57 day duration in PWA. It doesn't appear as if
the dates are different, but does anyone know why this happens?
will be managing projects. A very weird thing we have noticed is that once a
project is published and you check it in PWA, a task that had, say, a 50 day
duration in Project now has a 57 day duration in PWA. It doesn't appear as if
the dates are different, but does anyone know why this happens?