Jillos
Hi, am new to Project and having a few teething problems!
Am working on a project that involves working at the weekend, however, I
still wanted theweekend to appear shaded. This meant that project calculated
the duration of task incorrectly, (ie of they ran from fri to sun then it
called it 1 day)
I have remedied this i=on the Gantt by simply deleting the duration column,
however the wrong durations still appear on the calendar view.
DOES ANYONE HAVE ANY IDEA HOW i CAN REMOVE THE DURATION FROM THE CALENDAR
VIEW??
Any help much appreciated!
Jill
Am working on a project that involves working at the weekend, however, I
still wanted theweekend to appear shaded. This meant that project calculated
the duration of task incorrectly, (ie of they ran from fri to sun then it
called it 1 day)
I have remedied this i=on the Gantt by simply deleting the duration column,
however the wrong durations still appear on the calendar view.
DOES ANYONE HAVE ANY IDEA HOW i CAN REMOVE THE DURATION FROM THE CALENDAR
VIEW??
Any help much appreciated!
Jill