K
Kenneth R Adkins
I'm trying to set up task with an estimated or entered
duration and not have this action affect Start date or
Finish date. For example: It's possible that I'm working
on three task. All three task may start on the same day
and end on the same day. From start to finish each task
spanned three days. However, I only worked on each task a
few hours each day.
How do I enter a duration of say 6 hours for each task
and have the start and finish dates reflect the three
days for each task?
Do I have to insert a custom field to maintain my own end
date?
duration and not have this action affect Start date or
Finish date. For example: It's possible that I'm working
on three task. All three task may start on the same day
and end on the same day. From start to finish each task
spanned three days. However, I only worked on each task a
few hours each day.
How do I enter a duration of say 6 hours for each task
and have the start and finish dates reflect the three
days for each task?
Do I have to insert a custom field to maintain my own end
date?