S
Sean Bethell
I have just been given the responsibility of scheduling our PCB
manufacturing process and was looking to see if there is a template or some
example files for doing this,
I have made up a simple project but have found that I am unable to do some
things with-in the program.
Loading components = 25min.
Total units = 250
Time to load all = 6250min
Duration = 104.17hrs
How do you get Project to calculate this itself, as this is a common thing
for the manufacturing industry.
Thanks,
Sean.
(e-mail address removed)
manufacturing process and was looking to see if there is a template or some
example files for doing this,
I have made up a simple project but have found that I am unable to do some
things with-in the program.
Loading components = 25min.
Total units = 250
Time to load all = 6250min
Duration = 104.17hrs
How do you get Project to calculate this itself, as this is a common thing
for the manufacturing industry.
Thanks,
Sean.
(e-mail address removed)