K
karishma
hello
I am using MS Project 2003. I have already prepare the time line for my
project and in that i have kept the duration unit in "month" as default, then
even it gives some of the subtasks' duration in days and weeks.
I want to show different duration units for some of the task as it gives
duration in decimals (0.44 months).
so is it possible that project itself calculates the duration for the tasks
i want (eg. 0.44 months = how many no. of days). or do i have to do it
manually? also is it possible that some of the subtasks have duration in days
and their summary shoud have duration in months?
Thanks in advance
I am using MS Project 2003. I have already prepare the time line for my
project and in that i have kept the duration unit in "month" as default, then
even it gives some of the subtasks' duration in days and weeks.
I want to show different duration units for some of the task as it gives
duration in decimals (0.44 months).
so is it possible that project itself calculates the duration for the tasks
i want (eg. 0.44 months = how many no. of days). or do i have to do it
manually? also is it possible that some of the subtasks have duration in days
and their summary shoud have duration in months?
Thanks in advance